Back to home The Quarry threat... What's happening... Need for community response... The Background... SIRA & KCAP...

The Background...

Date

Event...

Circa 1940 Pioneer commence acquisition of lands in the foothills between Anstead and Mt. Crosby for the future purpose of quarrying.
1966
Application made by Pioneer for Quarry development at Mt Crosby and subsequently granted.
1972 Local community group successfully appealed, on a technicality, the decision to grant Pioneer permission for the establishment of a quarry.
December 1987 Application lodged by BMG (now Boral) to establish a quarry at Kholo Creek Resource Area at Mt. Crosby.
April 1988
SIRA formed to represent community concerns with Boral application and other potential quarrying in the area.
December 1988 State Government agrees after SIRA recommendation to undertake regional study into quarrying of the Kholo Creek resource.
1989 AGC Woodward Clyde appointed as consultant to undertake regional study of the Kholo Creek resource.
1990 ~ 1995 State Government failed to release findings of regional study.
March 1996 Freedom of Information application successfully made to uncover findings of regional study.
October 1996
Kholo Creek Advisory Panel (KCAP) formed. Role of KCAP is to assist the State Government in the identification and resolution of community issues associated with resource development.
1997 KCAP commissions a Quarry Needs Study by consultant Kershaw and Co., and an Economic Study by consultant Sinclair Knight Merz Economics.
March 1998 KCAP releases position paper supporting the proposition that a dedicated haul road south west from the resource area to the Warrego Hwy was the least cost option for material transport (per PB report terms of reference).
1998 Boral announces intention to seek approval to develop quarry.
1998
The Queensland Government, with approval of the KCAP and in recognition of the economic viability of the Kholo Creek resource compared with other alternatives, determined that in principle, the Kholo Creek resource could be developed. It also determined that product transport could only be via a dedicated transport corridor running from the resource area, south-west to the Warrego Highway.
June 2000 KCAP approves terms of reference for a State Government funded study into possible haul routes. PPK Environment & Infrastructure Pty Ltd (now Parsons Brinkerhoff (Australia) Ltd) is commissioned to undertake this study.
January 2002
In January 2002, SIRA received the draft PPK (now PB) report of the road transport planning study. SIRA believed the report to be inadequate and flawed and commenced investigation into areas of concern.
March 2002

SIRA investigates the vegetation survey provided by PPK and finds substantial shortcomings:

Summary of Review of Vegetation Survey and Vegetation Map.

April 2002
SIRA commissions an independent noise report and finds the PPK report to be inaccurate and flawed:

Summary of Noise Report

Full Noise Report

April 2002

SIRA advises KCAP of significant concerns with the PPK report.

Summary of SIRA feedback on PPK (now PB) report

June 2002
Issues raised by SIRA in respect of the PPK (PB) report, largely ignored apart from some minor amendment to vegetation survey. SIRA's request to have the PPK (PB) report regarded only as preliminary declined. Department of State Development advises that it will proceed with the release of the report to the public as a final report for community feedback. Position agreed by majority vote within KCAP, however it was agreed to add a foreword to the report noting that concerns with the report's veracity existed within the KCAP.
March 2003
PPK (PB) report released for community consultation. The study recommends route 4/20.
May 2003 Public submissions on PB report close, 75 submissions received
July 2003 First of a number of KCAP meetings to consider feedback and conisderable amendments to the PB report.
March 2004 PB report finalised,however KCAP fails to reach consensus on acceptance of report recommendations.

 


 

About SIRA:
Our Objective:
If there must be a quarry, to ensure the best possible outcome and least impact on the local community.
Contact us:
You can contact us via email at contact@sira.org.au. Please ensure you include your contact details in the body of the email.
How to join SIRA Inc.
It's free! Please send an email to membership@sira.org.au with your name, address and contact details.